By Natalia Forero, Local Democracy Reporter
The M27 will be closed for eleven days over Christmas to allow for the construction of a new underpass at Junction 10.
From 8pm on December 24 until 4am on January 4, the M27 will be shut in both directions between Junction 9 at Whiteley and Junction 11 at Fareham.
During the closure, engineers will carry out a huge operation to slide an 8,500-tonne pre-built concrete structure—known as a “box slide”—into place beneath the motorway. Once installed, the road will be rebuilt over the new underpass.
Drivers are being advised to plan ahead, as the closure is expected to cause significant disruption.
A diversion route will send traffic onto the A27, with warning signs placed as far away as the M25 and M4 to alert motorists coming into the area in advance.
Westbound drivers will still be able to exit the M27 at Junction 11 for Fareham and Gosport, and at Junction 9 for Whiteley and Park Gate.
However, there will be no westbound entry at Junction 11 for traffic heading towards Southampton or the A32 (Alton), and no eastbound entry at Junction 9 for vehicles travelling towards Portsmouth.
Andrew Jackson, National Highways Programme Manager. Photo:: LDRS
Andrew Jackson, program director from National Highways said: “We are working alongside Hampshire County Council to make sure we have plenty of preparation in place to keep that diversion open.”
Cllr Lulu Bowerman, cabinet member for highways at Hampshire County Council said: “We are getting ready for the Christmas closure. We are well aware that this would disrupt peoples’ Christmas travel plans, so I’m asking, if possible, to think carefully about how you travel over the Christmas period. Traffic would be less, but there would be still some traffic.
“We really appreciate everybody’s patience with this closure, but this would mean that we avoid months of roadworks and disruption on the M27, and the work could get competed on January 4.”
The underpass will create a new four-lane under the M27, alongside three new slip roads and the creation of a new dual carriageway, with four roundabouts, to link the slip roads to the existing road network, forming a ‘free flowing link’ at Junction 10.
The construction will also include walking and cycling paths, alongside new bridleways for horse riders, “we’ve thought about everyone”, the cabinet member for highways said.
For more information and updates visit hants.gov.uk/M27-J10-xmas
This article is from the Local Democracy Reporting Service. Some alterations and additions may have been made by our site - a partner in the BBC's Local News Partnerships scheme. BBC-funded LDRS journalists cover local authorities and public service organisations, with content shared by all partners.